Sandy Ridge Project Update – July 2019

  • Long lead air dome manufacturing complete and in transit to Port of Fremantle, WA
  • Modular buildings manufacturing nearing completion
  • Pre-gate enabling infrastructure upgrades and maintenance works continue as planned
  • EPC contractor continues to progress detailed design
  • Mt Dimer air strip earthworks almost complete
  • Site establishment works commences in line with current environmental regulatory approvals

The following is a brief summary of our recent activities at our Sandy Ridge Facility.

Overview

Sandy Ridge is Australia’s first dual open cut kaolin mine and arid near surface geological waste repository in a 70 million year old kaolin clay bed which is located 240 kilometers by road west north west of Kalgoorlie. The two staged works under contract will align with regulatory approvals.

Stage one enabling works

Stage one enabling works at Sandy Ridge are continuing as planned in line with the granted Works Approval (mining categories only). Stage two (construction) will commence in line with the granting of a lease and Works Approval (waste categories).

Stage two construction works

Stage two construction works include the remaining engineering; procurement,mining of the first open cut kaolin pit (waste cell), facility construction and commissioning of the Sandy Ridge facility site infrastructure.

Engineering, procurement and project management

Tellus’ EPC Contractor (GR Engineering Services Ltd) is progressing to plan with detailed design at 90% completed and procurement planning of sub-contractors and suppliers ongoing.

Long lead procurement – Air dome

Manufacturing has been completed and 15 containers are in transit. All containers are expected to be landed at Freemantle port by the 9th August 2019.

First pour of concrete anchor blocks has commenced.

Long lead procurement – modular buildings

Manufacturing of modular buildings is progressing well in preparation for transport to Sandy Ridge.

Mt Dimer airstrip

The Mt Dimer air strip earthworks are almost complete. Installation of aerodrome furniture and certification are scheduled for August. The upgrade will ensure the aerodrome meets CASA requirement for the type of aircraft to be used by Tellus for both the construction personnel in the short term and for our operational staff in the long term.

Site Establishment

Tell us working in conjunction with local contractors have commenced enabling works in readiness for construction led by our EPC contractor. This work includes a temporary on-site camp and clearing of the access roads in accordance with the approved Works Approval (mining categories). The remaining facility works will commence after the granting of the lease and Works Approval (waste categories). Both are expected later this year.

Site Visuals

Site Visuals have been engaged to capture base line data and the journey at Sandy Ridge. Photos from land and air, videos and time-lapses will be completed.

Investing millions in road, rail and air infrastructure

Tellus is committed to the safety of its staff and the local communities where it operates Tellus is investing millions of dollars in upgrading and maintaining regional, state owned infrastructure.

Becoming a supplier

Tellus supports the long-term, economic sustainability of the regions in which we operate. Consistent with Tellus’ “buy local hire local” policy, Tellus is pleased to support local WA businesses. Learn more >>

Community investment

One way Tellus makes a positive contribution in the Goldfield communities that we operate in is through our Community Investment program, which supports local projects and initiatives. To find out more visit >>

Employment and training opportunities

For information on employment, training & development and indigenous participation opportunities please visit >>

Tellus values

Tellus is a values based business. The core values are Safety, Service, People and Sustainability.

Transit route from Arizon’smanufacturing facility
Transit route from Arizon’smanufacturing facility in St Louis, USA, via ship from Norfolk port, USA to Fremantle port, WA
Temporary camp communications establishment
Temporary camp communications establishment
Internal fit out of kitchen
Internal fit out of kitchen
Tavern
Tavern
xample of a commuter aircraft
xample of a commuter aircraft ( Fairchild MetrolinerII ). Note the picture is not the Mt Dimer strip
Temporary camp establishment
Temporary camp establishment
Great Eastern Highway
Great Eastern Highway / Mt Walton Road Intersection upgrade
dorrie krahe
dorrie krahe